Scotland-specific

DNO Notification When You Replace a Solar Inverter in Scotland

Quick answer

If you replace an inverter with the same make and rating, you usually need no DNO notification at all. A different model at the same rating needs a G98 notification within 28 days of switch-on. Adding a battery or going above 3.68 kW per phase usually needs G99 approval from SP Energy Networks or SSEN before switch-on.

Scotland has two DNOs with different processes. Here is exactly what is required for each scenario.

Last updated: 1 November 2026

Row of terraced houses with chimneys and solar panels on their tiled roofs, typical of homes notifying the DNO

What are the key facts?

  • Same make and rating: no DNO notification needed
  • Different model, same rating: G98 notification after the work
  • Different rating or adding battery: G99 application before switch-on
  • Scotland has two DNOs: SP Energy Networks and SSEN
  • We handle all DNO paperwork at no extra charge
  • We install through MCS-certified partners across all of Scotland

Last updated: 1 November 2026

Short answer

A like-for-like inverter swap (same kW rating) needs only a G98 notification — submitted after the work, no waiting. If you change capacity or add a battery, you need G99 approval first (2–6 weeks). Scotland has two DNOs: SPEN (Central Belt) and SSEN (Highlands, north-east, islands).

The Two Scottish DNOs

SP Energy Networks (SPEN)

Glasgow, Edinburgh, Central Belt, Ayrshire, Borders, Dumfries & Galloway

  • G98 submissions via online portal
  • Typical turnaround: 5–10 working days
  • G99 applications: 20–45 working days

SSEN Distribution

Highlands, Aberdeen, Dundee, Perth, Fife, Orkney, Shetland, Western Isles

  • G98 submissions via online form
  • Typical turnaround: 5–15 working days
  • G99 applications: 30–65 working days (longer in constrained areas)
  • Island connections may require network study

Which Notification Do You Need?

  1. Scenario 1: Same make, same model, same kW rating

    Notification required: None

    A true like-for-like swap. No DNO paperwork. No FIT notification. Quickest route back to generating.

  2. Scenario 2: Different make or model, same kW rating (up to 3.68 kW/phase)

    Notification required: G98

    A G98 is a notification, not an application — you do not need approval before installing. Submit within 28 days of commissioning. We handle this as standard.

  3. Scenario 3: Different kW rating, or total exceeds 3.68 kW/phase

    Notification required: G99 application

    A G99 requires approval BEFORE energising. Common when upgrading to hybrid with battery. SSEN constrained zones (islands) can take 4–6 weeks.

  4. Scenario 4: Adding battery storage

    Notification required: G99 (usually)

    Most battery additions push total capacity above the G98 threshold. Also requires FIT/SEG licensee notification.

Highland and Island Logistics

Next-day delivery is not next-day north of Inverness or on any island. Parts from European distributors take 5–10 working days to reach Fort William, 7–14 days to reach Orkney or Shetland. We stock common replacement units (Solis, SolarEdge, Huawei, Fox ESS) at our central hub and ship direct, but lead times to remote areas are honest: typically 1–2 weeks from diagnosis to installation. We will not promise next-day when the freight reality is different.

Digital multimeter and circuit breakers used when testing a solar inverter grid connection

Protecting Your Feed-in Tariff

The DNO and your Feed-in Tariff licensee are separate. The DNO cares about what your system can push onto the network. Your FIT licensee, usually your original electricity supplier, cares that the generation meter and installed capacity match your FIT agreement. A replacement inverter does not end your FIT, but a change of make or rating should be reported so your payments are not queried.

After the job you receive the commissioning details, the new inverter make, model and serial number, and confirmation of the DNO notification. Send these to your FIT licensee in writing and keep a copy with your original MCS certificate. If the inverter rating changes, an updated MCS certificate may be needed. Our MCS-certified installation partner arranges this where it applies.

Homes on the Smart Export Guarantee rather than FIT should tell their SEG supplier about the new inverter too. Some suppliers ask for the new details before they continue paying for export.

DNO Notification Questions

Do I need to tell my DNO when replacing a solar inverter?

Yes, in most cases. A like-for-like replacement at the same kW rating needs only a G98 notification after the work is done. A different rating or adding battery storage requires a G99 application for approval before the new inverter is energised.

What is the difference between G98 and G99?

G98 is a notification for systems up to 3.68 kW per phase — you inform the DNO after the work. G99 is an application for larger systems or battery storage — you need written approval before switch-on. G99 typically takes 2 to 6 weeks.

Who is my DNO in Scotland?

Your DNO is either SP Energy Networks (central belt, south and west) or SSEN (Highlands, Islands, Tayside and Grampian). We identify your area from your postcode and handle the correct paperwork for whichever operator covers you.

Will replacing my inverter affect my Feed-in Tariff?

A like-for-life replacement at the same rating needs no notification to your FIT licensee. A different model or rating requires written notification so your generation meter readings stay valid. We handle this paperwork as part of every job.

We Handle All DNO Paperwork

No extra charge. G98 or G99, SPEN or SSEN — included in every quote.